992 resultados para Cost Overrun


Relevância:

100.00% 100.00%

Publicador:

Resumo:

Accurate owner budget estimates are critical to the initial decision-to-build process for highway construction projects. However, transportation projects have historically experienced significant construction cost overruns from the time the decision to build has been taken by the owner. This paper addresses the problem of why highway projects overrun their predicted costs. It identifies the owner risk variables that contribute to significant cost overrun and then uses factor analysis, expert elicitation, and the nominal group technique to establish groups of importance ranked owner risks. Stepwise multivariate regression analysis is also used to investigate any correlation of the percentage of cost overrun with risks, together with attributes such as highway project type, indexed cost, geographics location, and project delivery method. The research results indicate a correlation between the reciprocal of project budgets size and percentage cost overrun. This can be useful for owners in determining more realistic decision-to-build highway budget estimates by taking into account the economies of scale associated with larger projects.

Relevância:

70.00% 70.00%

Publicador:

Resumo:

The accuracy of early cost estimates is critical to the success of construction projects. The selected tender price (clients' building cost) is usually seen in previous research as a holistic dependent variable when examining early stage estimates. Unlike other components of construction cost, the amount of contingencies is decided by clients/consultants with consideration of early project information. Cost drivers of contingencies estimates are associated with uncertainty and complexity, and include project size, schedule, ground condition, construction site access, market condition and so on. A path analysis of 133 UK school building contracts was conducted to identify impacts of nine major cost drivers on the determination of contingencies by different clients/cost estimators. This research finds that gross floor area (GFA), schedule and requirement of air conditioning have statistically significant impacts on the contingency determination. The mediating role of schedule between gross floor area and contingencies (GFA→Schedule→Contingencies) was confirmed with the Soble test. The total effects of the three variables on contingencies estimates were obtained with the consideration of this indirect effect. The squared multiple correlation (SMC) of contingencies (=0.624) indicates the identified three variables can explain 62.4% variance of contingencies, and it is comparatively satisfactory considering the heterogeneity among different estimators, unknown estimating techniques and different projects

Relevância:

70.00% 70.00%

Publicador:

Resumo:

The design-build (DB) delivery method has been widely used in the United States due to its reputed superior cost and time performance. However, rigorous studies have produced inconclusive support and only in terms of overall results, with few attempts being made to relate project characteristics with performance levels. This paper provides a larger and more finely grained analysis of a set of 418 DB projects from the online project database of the Design-Build Institute of America (DBIA), in terms of the time-overrun rate (TOR), early start rate (ESR), early completion rate (ECR) and cost overrun rate (COR) associated with project type (e.g., commercial/institutional buildings and civil infrastructure projects), owners (e.g., Department of Defense and private corporations), procurement methods (e.g., ‘best value with discussion’ and qualifications-based selection), contract methods (e.g., lump sum and GMP) and LEED levels (e.g., gold and silver). The results show ‘best value with discussion’ to be the dominant procurement method and lump sum the most frequently used contract method. The DB method provides relatively good time performance, with more than 75% of DB projects completed on time or before schedule. However, with more than 50% of DB projects cost overrunning, the DB advantage of cost saving remains uncertain. ANOVA tests indicate that DB projects within different procurement methods have significantly different time performance and that different owner types and contract methods significantly affect cost performance. In addition to contributing to empirical knowledge concerning the cost and time performance of DB projects with new solid evidence from a large sample size, the findings and practical implications of this study are beneficial to owners in understanding the likely schedule and budget implications involved for their particular project characteristics.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

Nowadays, most of the infrastructure development projects undertaken are complex in nature. Practically, public clients who do not have a good understanding of the design and management may suffer severe losses, especially for infrastructure projects. There is a need for luring the right consultant to secure client's investment in infrastructure developments. Throughout the project life cycle, consultants play vital role from the inception to completion stage of a project. A few studies in Malaysia show that infrastructure projects involving irrigation and drainage have experience problems such as poor workmanship, delay and cost overrun due to the consultant's inability or the client incompetence of recruiting consultants in time. This highlights the need of aided decision making and an efficient system to select the best consultant by using Decision Support System (DSS). On the other hand, recent trends reveal that most DSS in construction only concentrate on decision model development. These models are impractical and unused as they are complicated or difficult for laymen such as project managers to utilize. Thus, this research attempts to develop an efficient DSS for consultant selection namely consultDeSS. Driven by the motivation and research aims, this study deployed Design Science Research Methodology (DSRM) dominant with a combination of case studies at the Malaysian Department of Irrigation and Drainage (DID). Two real projects involving irrigation and drainage infrastructure were used to design, implement and evaluate the artefact. The 3-tier consultDeSS was revised after the evaluation and the design was significantly improved based on user feedback. By developing desirable tools that fit client's needs will enhance the productivity and minimize conflict within groups and organisations. The tool is more usable and efficient compared to previous studies in construction. Thus, this research has demonstrated a purposeful artefact with a practical and valid structured development approach that is applicable in a variety of problems in construction discipline.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

For design-build (DB) projects, owners normally use lump sum and Guaranteed Maximum Price (GMP) as the major contract payment provisions. However, there was a lack of empirical studies to compare the project performance within different contract types and investigate how different project characteristics affect the owners’ selection of contract arrangement. Project information from Design-build Institute of America (DBIA) database was collected to reveal the statistical relationship between different project characteristics and contract types and to compare project performance between lump sum and GMP contract. The results show that lump sum is still the most frequently used contract method for DB projects, especially in the public sector. However, projects using GMP contract are more likely to have less schedule delay and cost overrun as compared to those with lump sum contract. The chi-square tests of cross tabulations reveal that project type, owner type, and procurement method affect the selection of contract types significantly. Civil infrastructure rather than industrial engineering project tends to use lump sum more frequently; and qualification-oriented contractor selection process resorts to GMP more often compared with cost-oriented process. The findings of this research contribute to the current body of knowledge concerning the effect of associated project characteristics on contract type selection. Overall, the results of this study provide empirical evidence from real DB projects that can be used by owners to select appropriate contract types and eventually improve future project performance.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

Chapter 1 presents a brief note on the state at which the construction industry stands at present, bringing into focus the significance of the critical study. Relevance of the study, area of investigation and objectives of the study are outlined in this chapter. The 2nd chapter presents a review of the literature on the relevant areas. In the third chapter an analysis on time and cost overrun in construction highlighting the major factors responsible for it has been done. A couple of case studies to estimate loss to the nation on account of delay in construction have been presented in the chapter. The need for an appropriate estimate and a competent contractor has been emphasised for improving effectiveness in the project implementation. Certain useful equations and thoughts have been formulated on this area in this chapter that can be followed in State PWD and other Govt. organisations. Case studies on project implementation of major projects undertaken by Government sponsored/supported organizations in Kerala have been dealt with in Chapter 4. A detailed description of the project of Kerala Legislature Complex with a critical analysis has been given in this chapter. A detailed account of the investigations carried out on the construction of International Stadium, a sports project of Greater Cochin Development Authority is included here. The project details of Cochin International Airport at Nedumbassery, its promoters and contractors are also discussed in Chapter 4. Various aspects of implementation which led the above projects successful have been discussed in chapter 5. The data collected were analysed through discussion and perceptions to arrive at certain conclusions. The emergence of front-loaded contract and its impact on economics of the project execution are dealt with in this chapter. Analysis of delays in respect of the various project narrated in chapter 3 has been done here. The root causes of the project time and overrun and its remedial measures are also enlisted in this chapter. Study of cost and time overrun of any construction project IS a part of construction management. Under the present environment of heavy investment on construction activities in India, the consequences of mismanagement many a time lead to excessive expenditure which are not be avoidable. Cost consciousness, therefore has to be keener than ever before. Optimization in investment can be achieved by improved dynamism in construction management. The successful completion of coristruction projects within the specified programme, optimizing three major attributes of the process - quality, schedule and costs - has become the most valuable and challenging task for the engineer - managers to perform. So, the various aspects of construction management such as cost control, schedule control, quality assurance, management techniques etc. have also been discussed in this fifth chapter. Chapter 6 summarises the conclusions drawn from the above criticalr1 of rhajor construction projects in Kerala.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

The technique of linear responsibility analysis is used for a retrospective case study of a private development consisting of an extension to an existing building to provide a wholesale butchery facility. The project used a conventionally organized management process. The organization structure adopted on the project is analysed using concepts from the systems theory, which are included in Walkers theoretical model of the structure of building project organizations. This model proposes that the process of building provision can be viewed as systems and sub-systems that are differentiated from each other at decision points. Further to this, the sub-systems can be viewed as the interaction of managing system and operating system. Using Walkers model, a systematic analysis of the relationships between the contributors gives a quantitative assessment of the efficiency of the organizational structure used. The project's organization structure diverged from the models propositions resulting in delay to the project's completion and cost overrun but the client was satisfied with the project functionally.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

Ten projects constructed in Ghana between 2003 and 2010 are examined and analysed to ascertain the reliability of estimated costs provided for the projects. Cost estimates for five of the projects were calculated by consultants and cost estimates for the five remaining projects were calculated by contractors. Cost estimates prepared by contractors seemed to be closer to actual costs than estimates calculated by consultants. Projects estimated by consultants experienced an average cost overrun of 40% and time overrun of 62% whereas projects priced by contractors experienced an average cost overrun of 6% and time overrun of 41%. It seemed that contractors had a better understanding of the actual construction processes and a clearer expectation of the needs of the client hence an ability to calculate estimates that were closer to reality. Construction clients in Ghana should rely on contractors for more realistic cost estimates as estimates by consultants may be inaccurate. Where consultants are employed, an allowance of up 40% should be added to the estimated costs as a margin for inaccuracy.

Relevância:

60.00% 60.00%

Publicador:

Resumo:

Las desviaciones de tiempo y coste constituyen un fenómeno muy frecuente en la industria de la construcción. Existe un gran número de proyectos que no se terminan en el plazo y el tiempo estipulados, y esto parece que se ha convertido más en la norma que en la excepción. Los proyectos de construcción son heterogéneos por naturaleza y pueden llegar a ser muy complejos, involucrando numerosos procesos y expuestos a infinidad de variables y factores que pueden afectar el cumplimiento de los objetivos de tiempo y coste. Las desviaciones de tiempo y coste no favorecen ni al promotor ni al resto de equipos participantes del proyecto, dando lugar además la mayoría de las veces a situaciones de conflictos y relaciones adversas entre participantes del proyecto. Es por todo ello que surge la necesidad de atender a una estrategia de gestión de riesgos eficaz, como herramienta esencial de la gestión de proyectos para contribuir al éxito de los mismos. Es preciso considerar también que los proyectos de construcción pueden presentar distintas características específicas según el tipo de proyecto de que se traten. El presente trabajo de investigación estudia concretamente los proyectos de edificios de uso hotelero, los cuales pueden presentar estructuras organizativas muy diversas, incluyendo numerosos agentes participantes y procesos que a su vez se desarrollan en un entorno que ya es muy dinámico por su propia naturaleza. En el sector hotelero el cumplimiento de los objetivos de tiempo y coste del proyecto son especialmente importantes ya que cualquier retraso en la fecha de apertura estimada del hotel se traducirá en pérdidas importantes de negocio y cuota de mercado y podrá llevar asociadas también repercusiones importantes en otros aspectos relacionados con la operativa hotelera. Si se conocen las causas que originan tales desviaciones de tiempo y coste, se podrán establecer las correspondientes medidas de actuación para anticiparnos a ellas y que no se produzcan, siendo ésta la base del propósito de esta tesis. Así, la identificación de riesgos supone el primer paso para una gestión de riesgos eficaz, fundamental para contribuir al éxito de un proyecto. El contexto de la investigación delimita como lugar geográfico de estudio España, donde el sector turístico constituye un motor importante de la economía y en el que la eficiencia y competitividad debe estar reflejada también en el proceso del proyecto edificatorio, minimizándose los retrasos y sobrecostes. El presente estudio investiga por tanto los factores de riesgo más críticos que dan lugar a desviaciones de tiempo y coste en proyectos de edificios de uso hotelero en España. A partir del análisis de la literatura existente se genera una propuesta de identificación de factores de riesgo, que se analiza mediante un análisis cualitativo basado en la opinión de expertos y estudio de casos específicos. De los resultados de este análisis se determinan los niveles críticos para cada factor de riesgo, se comparan además las percepciones de niveles de riesgo según distintos tipos de grupos profesionales, y se establece un procedimiento en cuanto a prioridad de acción de respuesta. Así, se desarrolla una propuesta final de identificación y matriz de factores de riesgo con el objetivo de que pueda servir de base a propietarios, empresas gestoras y otros participantes de proyectos hoteleros para diseñar un plan de gestión de riesgos eficaz, contribuyendo de este modo al éxito del proyecto en cuanto a cumplimiento de objetivos de tiempo y coste programados. ABSTRACT Cost and schedule overruns constitute a very frequent phenomenon in the construction industry. A large number of construction projects do not finish on the estimated time and cost, and this scenario seems to be becoming the norm rather than the exception. Construction projects are heterogeneous by nature and they can become very complex as they involve a large number of processes which are subject to many variables and factors that may give rise to time and cost overruns. Time and cost overruns cause dissatisfaction not only to owners but all stakeholders involved in the project, leading most of the times to undesirable situations of conflicts and adversarial relationships between project participants. Hence, it becomes necessary to adopt an effective risk management strategy as an essential part of project management in order to achieve project success. Construction projects may have different characteristics depending on the type of project. This research specifically focuses on hotel construction projects. Hotel projects usually involve complex organizational structures, including many project participants and processes which develop in an environment that is already dynamic by nature. In this type of projects, the achievement of time and cost objectives is particularly important, as any delay of the hotel opening date will result in significant loss of business and market share and may also involve key important implications related to hotel operations. If the risk factors that lead to time and cost overrun are known in advance, preventive actions could be established in order to avoid them, so that time and cost overruns are minimized. This constitutes the aim of this research, being risk identification the first step of any effective risk management strategy for project success. The context of this research is focused on a particular geographical area, being this Spain. Tourism in Spain is a major contributor to the Spanish economy, and efficiency and competiveness should also be reflected in the building processes of the hotel industry, where delays and cost overruns should be kept to the minimum. The aim of this study is to explore the most critical risk factors leading to time and cost overruns in hotel construction projects in Spain. From the analysis of the literature review, a proposal of a risk identification framework is developed, which will be further analyzed by a qualitative assessment based on expert opinions and the study of specific case studies. From the results of this assessment, the levels of risk criticality are determined for the identified factors, a comparison of the perceptions of risk levels among different groups of respondents is also carried out, and a procedure for prioritization of factors in terms of needs of response is established. A final proposal of a risk register matrix framework is then developed in order to assist hotel owners, project management companies or other hotel project stakeholders, and provide them with a base to design their own specific risk management plans, contributing in this way to project success with regards to the achievement of cost and time objectives.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

This research was undertaken to encompass and identify challenges and impact factors that affect the successful outcomes of heritage building projects, especially those related to finding major causes of delays and cost overruns across projects in all Australian states. This project determined and analysed the causes of such delays and programme issues emanating from the planning and execution phases, whilst also analysing the requirements for management of multiple stakeholder relationships and the influence of unforeseen technical factors. The research proposes "call for action" guidance and was validated by experienced experts in heritage building projects in Australia. The proposed guidance is designed to ensure that realistic cost targets and delivery timeframes are set in future heritage projects, and necessary interventions made at appropriate project stages to ensure decisions are made that will help to prevent overtime and cost overuns.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

Poor project planning, implementation and control and the subsequent cost and time overruns are ubiquitous features that have been posing serious concern at all levels - state, national and international. It results in wastage of the nation's scarce resources and retards the socio-economic progress. Although several studies peripheral on project overruns have been made at the national level, no serious attempt has been made at the state level to identify the magnitude of overruns, their causes and impacts on industrial projects. The present study "Time and Cost Overruns of Industrial Projects in Kerala" is an earnest attempt to probe in depth the time and cost overruns and their impact on industrial projects. The study places emphasise on the identification of the real reasons behind the cost and time overruns. It also covers the present project management practices of industrial projects in Kerala.