Evaluation of risk factors leading to cost overrun in delivery of highway construction projects
Data(s) |
01/04/2010
|
---|---|
Resumo |
Accurate owner budget estimates are critical to the initial decision-to-build process for highway construction projects. However, transportation projects have historically experienced significant construction cost overruns from the time the decision to build has been taken by the owner. This paper addresses the problem of why highway projects overrun their predicted costs. It identifies the owner risk variables that contribute to significant cost overrun and then uses factor analysis, expert elicitation, and the nominal group technique to establish groups of importance ranked owner risks. Stepwise multivariate regression analysis is also used to investigate any correlation of the percentage of cost overrun with risks, together with attributes such as highway project type, indexed cost, geographics location, and project delivery method. The research results indicate a correlation between the reciprocal of project budgets size and percentage cost overrun. This can be useful for owners in determining more realistic decision-to-build highway budget estimates by taking into account the economies of scale associated with larger projects. |
Formato |
application/pdf |
Identificador | |
Publicador |
American Society of Civil Engineers (ASCE) |
Relação |
http://eprints.qut.edu.au/37745/2/37745.pdf DOI:10.1061/(ASCE)CO.1943-7862.0000160 Creedy, Garry D., Skitmore, Martin, & Wong, Johnny K.W. (2010) Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. Journal of Construction Engineering and Management, 136(5), pp. 528-536. |
Direitos |
Copyright 2010 American Society of Civil Engineers |
Fonte |
Faculty of Built Environment and Engineering; School of Urban Development |
Palavras-Chave | #120200 BUILDING #Construction Management #Cost Estimates #Cost Overrun #Highway Construction #Risk Management |
Tipo |
Journal Article |