339 resultados para Highway bridge


Relevância:

20.00% 20.00%

Publicador:

Resumo:

The Iowa Department of Transportation used a high molecular weight methacrylate (HMWM) resin to seal a 3,340 ft. x 64 ft. bridge deck in October 1986. The sealing was necessary to prevent deicing salt brine from entering a substantial number of transverse cracks that coincided with the epoxy coated top steel and unprotected bottom steel. HMWM resin is a three component product composed of a monomer, a curnene hydroperoxide initiator and a cobalt naphthenate promoter. The HMWM was applied with a dual spray bar system and flat-fan nozzles. Initiated monomer delivered through one spray bar was mixed in the air with promoted monomer from the other spray bar. The application rate averaged 0.956 gallons per 100 square feet for the tined textured driving lanes. Dry sand was broadcast on the surface at an average coverage of 0.58 lbs. per square yard to maintain friction. Coring showed that the H.MWM resin penetrated the cracks more than two inches deep. Testing of the treated deck yielded Friction Numbers averaging 33 with a treaded tire compared to 36 prior to treatment. An inspection soon after treatment found five leaky cracks in one of the 15 spans. One inspection during a steady rain showed no leakage, but leakage from numerous cracks occurred during a subsequent rain. A second HMWM application was made on two spans to determine if a double application would prevent leakage. This evaluation has not been completed.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

A contract for Project HR-20 "Treating Loess, Fine Sands and Soft Limestones with Liquid Binders" of the Iowa Highway Research Board was awarded in December, 1951, to the Iowa Engineering Experiment Station of Iowa State University as its Project 295-S. By 1954 the studies of the fine materials and asphalts had progressed quite well, and a method of treating the fine materials, called the atomization process, had been applied. A study was begun in 1954 to see if some of the problems of the atomization process could be solved with the use of foamed asphalt. Foamed asphalt has several advantages. The foaming of asphalt increases its volume, reduces its viscosity, and alters its surface tension so that it will adhere tenaciously to solids. Foamed asphalt displaces moisture from the surface of a solid and coats it with a thin film. Foamed asphalt can permeate deeply into damp soils. In the past these unusual characteristics were considered nuisances to be avoided if possible.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Use of bridge deck overlays is important in maximizing bridge service life. Overlays can replace the deteriorated part of the deck, thus extending the bridge life. Even though overlay construction avoids the construction of a whole new bridge deck, construction still takes significant time in re-opening the bridge to traffic. Current processes and practices are time-consuming and multiple opportunities may exist to reduce overall construction time by modifying construction requirements and/or materials utilized. Reducing the construction time could have an effect on reducing the socioeconomic costs associated with bridge deck rehabilitation and the inconvenience caused to travelers. This work included three major tasks with literature review, field investigation, and laboratory testing. Overlay concrete mix used for present construction takes long curing hours and therefore an investigation was carried out to find fast-curing concrete mixes that could reduce construction time. Several fast-cuing concrete mixes were found and suggested for further evaluation. An on-going overlay construction project was observed and documented. Through these observations, several opportunities were suggested where small modifications in the process could lead to significant time savings. With current standards of the removal depth of substrate concrete in Iowa, it takes long hours for the removal process. Four different laboratory tests were performed with different loading conditions to determine the necessary substrate concrete removal depth for a proper bond between the substrate concrete and the new overlay concrete. Several parameters, such as failure load, bond stress, and stiffness, were compared for four different concrete removal depths. Through the results and observations of this investigation several conclusions were made which could reduce bridge deck overlay construction time.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

In 1982 the Iowa DOT allowed a successful bidder the option of submitting materials and proportions using fly ash to produce a portland cement concrete (PCC) paving mixture to meet a specified compressive strength. The contractor, Irving F. Jensen, received approval for the use of a concrete mixture utilizing 500 lbs. of portland cement and 88 lbs. of fly ash as a replacement of 88 lbs. of portland cement. The PCC mixture was utilized on the Muscatine County US 61 relocation bypass paved as project F-61-4(32)--20-70. A Class "C" fly ash obtained from the Chillicothe electric generating plant approximately 100 miles away was used in the project. This use of fly ash in lieu of portland cement resulted in a cost savings of $64,500 and an energy savings of approximately 16 billion BTU. The compressive strength of this PCC mixture option was very comparable to concrete mixtures produced without the use of fly ash. The pavement has been performing very well. The substitution of fly ash for 15% of the cement has been allowed as a contractor's option since 1984. Due to the cost savings, it has been used in almost all Iowa PCC paving since that time.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Four series of five specimens each were investigated for static and fatigue strength. These four series differed in that there were two variables, the first being the subsidence of concrete around reinforcing bars and the second being shrinkage due to two different curing conditions. The combinations of these variables were then compared to each other by use of, load-deflection curves and S-H fatigue curves.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

As a result of the construction of the Saylorville Dam and Reservoir on the Des Moines River, six highway bridges crossing the river were scheduled for removal. Two of these were incorporated into a comprehensive test program to study the behavior of old pin-connected high-truss single-lane bridges. The test program consisted of ultimate load tests, service load tests and a supplementary test program. The results reported in this report cover the service load tests on the two bridges as well as the supplementary tests, both static and fatigue, of eyebar members removed from the two bridges. The field test results of the service loading are compared with theoretical results of the truss analysis.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

In the search for new soil stabilizing agents the effects of six organic cations on plastic limit, liquid limit, shrinkage limit, air-dry strength and rate of slaking of a highly plastic clay subsoil were studied. In all cases the plasticity index and shrinkage were reduced by the treatments. The air-dry strength was lowered in varying degree, which was the only undesirable effect noted. With one exception resistance to slaking was improved. It is concluded that large organic cations show promise as possible stabilizing agents for highly plastic fine-grained soils.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

This bulletin is a compilation of the reports on completed research done for the Iowa State Highway Research Board Project HR-1, "The Loess and Glacial Till Materials of Iowa; an Investigation of Their Physical and Chemical Properties and Techniques for Processing Them to Increase Their All-Weather Stability for Road Construction.” The research, started in 1950, was done by the Iowa Engineering Experiment Station under its project 283-S. The project was supported by funds from the Iowa State Highway Commission.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

In this report, the authors present the data accumulated from a one-year study of runoff quantity and quality from two sections of Interstate Highway 35 near Ames with an interpretation of the significance of the data. The report will discuss the site setup, operational aspects of data collection, and problems encountered. In addition, recommendations are included to optimize information gained from the study.