Resumo:
History has shown that projects move in and out of poor status through the life of the project. Predicting the success or failure of a project to complete on time because of its recent history on the contract status report could provide our project managers another tool for monitoring contract progress. In many instances, poor contract progress results in the loss of contract time and late completion of projects. This research evaluates the combinations of work type, point in time physical work begins, recent poor status, and contract bid amount as indicators of late project completion.