An Analysis of the Early Prediction of Highway Construction Project Completion using the Contract Status Report
Data(s) |
28/09/2016
28/09/2016
01/02/2016
|
---|---|
Resumo |
History has shown that projects move in and out of poor status through the life of the project. Predicting the success or failure of a project to complete on time because of its recent history on the contract status report could provide our project managers another tool for monitoring contract progress. In many instances, poor contract progress results in the loss of contract time and late completion of projects. This research evaluates the combinations of work type, point in time physical work begins, recent poor status, and contract bid amount as indicators of late project completion. |
Formato |
application/pdf Document |
Identificador | |
Idioma(s) |
English |
Publicador |
South Carolina State Library |
Relação |
South Carolina State Documents Depository |
Direitos |
Public Domain This is a government document; please see the rights statement available here: http://www.statelibrary.sc.gov/statement-of-rights. |
Palavras-Chave | #Roads--South Carolina--Design and construction #Express highways--South Carolina--Design and construction #South Carolina Department of Transportation #Project management--South Carolina #Road construction contracts--South Carolina |
Tipo |
Text |