932 resultados para 090502 Construction Engineering
Resumo:
Construction delays are a critical problem for Malaysian public sector projects. These delays have been blamed mainly on inefficient traditional construction practices that continue to dominate the current industry. This paper reports the progress to date of a Ph.D. research project aimed at developing a framework to utilize Supply Chain Management (SCM) tools to improve the time performance of Malaysian Government projects. The potential of SCM has been identified for public sector governance and its use in Malaysia is now being considered within the strategy of the Malaysian Construction Industry Master Plan (2006-2015). Encouraged by success in the UK, there is a cautious optimism concerning the successful application of SCM in Malaysia. This paper considers delay as a problem in Malaysian public sector projects, establishes the need to embrace SCM and then elucidates the need and strategies for the development of a delay reduction framework. A literature review, survey mechanism and structured interview schedule will be undertaken to achieve the research objectives. The final research outcome will be a framework that addresses root delay contributors (“pathogens”) and applies SCM tools for their mitigation.
Resumo:
Downtime (DT) caused by non-availability of equipment and equipment breakdown has non-trivial impact on the performance of construction projects. Earlier research has often addressed this fact, but it has rarely explained the causes and consequences of DT – especially in the context of developing countries. This paper presents a DT model to address this issue. Using this model, the generic factors and processes related to DT are identified, and the impact of DT is quantified. By applying the model framework to nine road projects in Nepal, the impact of DT is explored in terms of its duration and cost. The research findings highlight how various factors and processes interact with each other to create DT, and mitigate or exacerbate its impact on project performance. It is suggested that construction companies need to adopt proactive equipment management and maintenance programs to minimize the impact of DT.
Resumo:
It is well-known that the use of off-site manufacture (OSM) techniques can assist in timely completion of a construction project though the utilisation of such techniques may have other disadvantages. Currently, OSM uptake within the Australian construction industry is limited. To successfully incorporate OSM practices within a construction project, it is crucial to understand the impact of OSM adoption on the processes used during a construction project. This paper presents how a systematic process-oriented approach may be able to support OSM utilisation within a construction project. Process modelling, analysis and automation techniques which are well-known within the Business Process Management (BPM) discipline have been applied to develop a collection of construction process models that represent the end-to-end generic construction value chain. The construction value chain enables researchers to identify key activities, resources, data, and stakeholders involved in construction processes in each defined construction phase. The collection of construction process models is then used as a basis for identification of potential OSM intervention points in collaboration with domain experts from the Australian construction industry. This ensures that the resulting changes reflect the needs of various stakeholders within the construction industry and have relevance in practice. Based on the input from the domain experts, these process models are further refined and operational requirements are taken into account to develop a prototype process automation (workflow) system that can support and coordinate OSM-related process activities. The resulting workflow system also has the potential to integrate with other IT solutions used within the construction industry (e.g., BIM, Acconex). As such, the paper illustrates the role that process-oriented thinking can play in assisting OSM adoption within the industry.
Resumo:
The construction industry has long been burdened with inherent adversarial relationships among the parties and the resulting disputes. Dispute review boards (DRBs) have emerged as alternatives to settle construction-related disputes outside courts. Although DRBs have found support in some quarters of the construction industry, the quantitative assessment of the impact of DRBs has not been adequately addressed. This paper presents the results of a research project undertaken to assess the impact of DRBs on the construction program of a large-scale highway agency. Three dimensions of DRB impact were assessed: (1) influence on project cost and schedule performance, (2) effectiveness of DRBs in preventing and resolving construction disputes, and (3) costs of DRB implementation. The analyses encompass data from approximately 3,000 projects extending over a 10-year period (2000–2009). Quantitative measures of performance were developed and analyzed for each category. Projects that used DRBs faced reduced costs and schedule growth (6.88 and 12.92%, respectively) when compared to non-DRB projects (11.53 and 28.96%). DRBs were also found to be effective in avoiding and settling disputes; the number of arbitration cases reduced consistently after DRB implementation, and DRBs have a success rate of 97% in settling disputes for which DRBs were used. Moreover, costs of DRBs were found to comprise a relatively small fraction (i.e., approximately 0.3%) of total project budgets. It was concluded that DRBs were effective dispute prevention and resolution alternatives with no significant adverse effects on project performance.
Resumo:
The complex supply chain relations of the construction industry, coupled with the substantial amount of information to be shared on a regular basis between the parties involved, make the traditional paper-based data interchange methods inefficient, error prone and expensive. The successful information technology (IT) applications that enable seamless data interchange, such as the Electronic Data Interchange (EDI) systems, have generally failed to be successfully implemented in the construction industry. An alternative emerging technology, Extensible Markup Language (XML), and its applicability to streamline business processes and to improve data interchange methods within the construction industry are analysed, as is the EDI technology to identify the strategic advantages that XML technology provides to overcome the barriers to implementation. In addition, the successful implementation of XML-based automated data interchange platforms for a large organization, and the proposed benefits thereof, are presented as a case study.
Resumo:
Temporary Traffic Control Plans (TCP’s), which provide construction phasing to maintain traffic during construction operations, are integral component of highway construction project design. Using the initial design, designers develop estimated quantities for the required TCP devices that become the basis for bids submitted by highway contractors. However, actual as-built quantities are often significantly different from the engineer’s original estimate. The total cost of TCP phasing on highway construction projects amounts to 6–10% of the total construction cost. Variations between engineer estimated quantities and final quantities contribute to reduced cost control, increased chances of cost related litigations, and bid rankings and selection. Statistical analyses of over 2000 highway construction projects were performed to determine the sources of variation, which later were used as the basis of development for an automated-hybrid prediction model that uses multiple regressions and heuristic rules to provide accurate TCP quantities and costs. The predictive accuracy of the model developed was demonstrated through several case studies.
Resumo:
Highway construction projects have direct impacts on adjacent businesses. The nature and the degree of impact depend on individual business characterization and project specific factors. The type of business is also a relevant factor in predicting the impact of transportation construction projects. This paper presents the results of research focused on developing an in-depth understanding of these relationships. The study includes project case studies of three transportation construction projects in Florida. Surveys were conducted with all adjacent businesses, which were combined with analyses of the business accommodation procedures employed by State Highway Agencies (SHAs) nationwide to provide measure the efficiency of present rules. The results include an analysis of differing priorities for different classification of businesses and development of design and construction management best practices to better accommodate businesses during highway construction. A pilot project that employed business accommodation principles devised in this research, and improvements to business accommodations observed were compared to cases where no measures were taken.
Resumo:
Transportation construction is substantially different from other construction fields due to widespread use of unit price bidding and competitive contract awarding. Thus, the potential for change orders has been the main source of unbalanced bidding for contractors, which can be described as substantial increases in work quantity or reasonable changes to the initial design provided by the State Highway Agencies (SHAs). It is important to understand the causes of the change orders as cost related issues are the main reason for contract disputes. We have analyzed a large dataset from a major SHA to identify project related and environmental factors that affect the change order costs. The results of the study can be instrumental in assessing the increased costs associated with change orders and better management measures can be taken to mitigate their effects.
Resumo:
An investigation of the construction data management needs of the Florida Department of Transportation (FDOT) with regard to XML standards including development of data dictionary and data mapping. The review of existing XML schemas indicated the need for development of specific XML schemas. XML schemas were developed for all FDOT construction data management processes. Additionally, data entry, approval and data retrieval applications were developed for payroll compliance reporting and pile quantity payment development.
Resumo:
The continuous changing impacts appeared in all solution understanding approaches in the projects management field (especially in the construction field of work) by adopting dynamic solution paths. The paper will define what argue to be a better relational model for project management constraints (time, cost, and scope). This new model will increase the success factors of any complex program / project. This is a qualitative research adopting a new avenue of investigation by following different approach of attributing project activities with social phenomena, and supporting phenomenon with field of observations rather than mathematical method by emerging solution from human, and ants' colonies successful practices. The results will show the correct approach of relation between the triple constraints considering the relation as multi agents system having specified communication channels based on agents locations. Information will be transferred between agents, and action would be taken based on constraint agents locations in the project structure allowing immediate changes abilities in order to overcome issues of over budget, behind schedule, and additional scope impact. This is complex adaptive system having self organizes technique, and cybernetic control. Resulted model can be used for improving existing project management methodologies.
Resumo:
Data fusion can be defined as the process of combining data or information for estimating the state of an entity. Data fusion is a multidisciplinary field that has several benefits, such as enhancing the confidence, improving reliability, and reducing ambiguity of measurements for estimating the state of entities in engineering systems. It can also enhance completeness of fused data that may be required for estimating the state of engineering systems. Data fusion has been applied to different fields, such as robotics, automation, and intelligent systems. This paper reviews some examples of recent applications of data fusion in civil engineering and presents some of the potential benefits of using data fusion in civil engineering.