998 resultados para Marcilly, Aug.


Relevância:

10.00% 10.00%

Publicador:

Resumo:

Letter sent from the Port Dalhousie and Thorold Railway to the Town Council of St. Catharines which states that the estimate that was submitted does not embrace the damages done to the buildings along Line no. 1 from Port Dalhousie to Chisholm Corner. The estimates are included in the document, Aug. 17, 1854.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Port Dalhousie and Thorold Railway estimate of work done to date with an approximation of probable damage sustained by suspending the track, Aug. 22, 1854.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Clipping from a Town Council meeting at which estimates of the costs of Railway Line no. 1 and Line no. 2 were submitted by the office of Port Dalhousie and Thorold Railway. The estimate was submitted by S.D. Woodruff and George Rykert, president. There is also a disclaimer in which Calvin Phelps claims to have resigned as director of the Port Dalhousie and Thorold Railway when he discovered that the company had no intention to adhere to the original plan for building and running the road, Aug. 1854.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Estimate of work done on the Port Dalhousie and Thorold Railway by Messrs. Brown and McDonell, contractors, on sections 1, 2, and 3 ending at St. Catharines during the month ending Aug. 31, 1854.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Port Dalhousie and Thorold Railway wages paid to John Brown (2 pages, handwritten) from Aug. 1855 – May 1856.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and Thorold Station of the Great Western Railway by John Brown for July, 1856. This is accompanied by a chart of an itemized list and a sheet of calculations, Aug. 1856.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Chart of estimate for work done on the Port Dalhousie and Thorold Railway by Alex Morrison regarding construction of the coal wharf for the month of Jul. 1856. The document is signed by S.D. Woodruff, Aug. 24, 1856.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Letter to the Port Dalhousie and Thorold Railway for work the sluice at the aqueduct, on the hillside. This is signed by R. Collier, Aug. 28, 1856.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Letter to S.D. Woodruff from Fred Holmes noting how many days work were done by him, William Stoker and Thomas Secord, Aug. 27, 1860.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Amount paid to Frederick Holmes by the Welland Railway Company for 26 days of service during February, March and April for excavations made at Port Dalhousie (1 page, handwritten). This is signed by S.D. Woodruff, Aug. 28, 1860.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Minutes of the Board of Directors of the Port Hope, Lindsay and Beaverton Railway Company held in Port Hope, Aug 9, 1855.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Agreement to undertake construction and complete the road in accordance with the engineer or the Port Robinson and Thorold macadamized road. This is signed by John Williams, Aug. 11, 1855.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Letter containing specifications for the construction of the Port Robinson and Thorold macadamized road sent to Matthews from S.D. Woodruff (3 pages, handwritten), Aug. 25, 1855.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Letter from S.D. Woodruff to the president and directors of the Port Robinson and Thorold Macadamized Road Committee regarding extra work done (3 pages, handwritten), Aug. 6, 1857.

Relevância:

10.00% 10.00%

Publicador:

Resumo:

Chart of estimate #10 of work done by John Williams. Aug. 1856.