1000 resultados para Price, Benjamin Woodruff
Resumo:
Letter to S.D. Woodruff from F. Lalor, assistant engineer. This is an estimate of work done by John Brown between Grantham and Thorold, Mar. 4, 1856.
Resumo:
Letter of estimate sent to S.D. Woodruff for the total cost of construction and equipment of the extension of the line to Port Colborne [this is unsigned]. There is an envelope with this letter that suggests that it is from Mr. Shanly, Mar. 12, 1857.
Resumo:
Letter regarding an estimate of lowering the grade as suggested by William Hamilton Merritt. This was sent to S.D. Woodruff from F. Shanly, May 22, 1857.
Resumo:
Note to S.D. Woodruff regarding the plan of operation. First, “draw up a report showing the cost of work”. This note is unsigned, n.d.
Resumo:
Receipt for payment from S.D. Woodruff from Hiram Slate, Jan. 1859
Resumo:
Letter to S.D. Woodruff from Fred Holmes regarding the work done on the east side of the rail track. He gives the measurement of work done by W. Robinson, May 18, 1860.
Resumo:
Letter to S.D. Woodruff from Fred Holmes noting how many days work were done by him, William Stoker and Thomas Secord, Aug. 27, 1860.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of April and May, 1854, signed by S.D. Woodruff, May 31, 1854.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of June, July, August and September, 1854, signed by S.D. Woodruff, Sept. 30, 1854.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of October, November and December, 1854, signed by S.D. Woodruff, Jan. 8, 1855.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of October, January, February and March, 1855, signed by S.D. Woodruff, Mar. 22, 1855.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of April and May, 1855, signed by S.D. Woodruff, June 13, 1855.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of June, July and August, 1855, signed by S.D. Woodruff. There is an envelope included with this document, Aug. 21, 1855.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of March, April and May, 1856, signed by S.D. Woodruff, June 3, 1856.
Resumo:
Port Dalhousie and the Thorold Railway pay roll for services of engineering and contingencies furnished for the months of June, July and August, 1856, signed by S.D. Woodruff, Sept. 2, 1856.