923 resultados para Construction Project Delivery


Relevância:

90.00% 90.00%

Publicador:

Resumo:

Several parties (stakeholders) are involved in a construction project. The conventional Risk Management Process (RMP) manages risks from a single party perspective, which does not give adequate consideration to the needs of others. The objective of multi-party risk management is to assist decision-makers in managing risk systematically and most efficiently in a multi-party environment. Multi-party Risk Management Processes (MRMP) consist of risk identification, structuring, analysis and developing responses from all party perspectives. The MRMP has been applied to a cement plant construction project in Thailand to demonstrate its effectiveness.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

An inherent weakness in the management of large scale projects is the failure to achieve the scheduled completion date. When projects are planned with the objective of time achievement, the initial planning plays a vital role in the successful achievement of project deadlines. Cost and quality are additional priorities when such projects are being executed. This article proposes a methodology for achieving time duration of a project through risk analysis with the application of a Monte Carlo simulation technique. The methodology is demonstrated using a case application of a cross-country petroleum pipeline construction project.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

This study proposes an integrated analytical framework for effective management of project risks using combined multiple criteria decision-making technique and decision tree analysis. First, a conceptual risk management model was developed through thorough literature review. The model was then applied through action research on a petroleum oil refinery construction project in the Central part of India in order to demonstrate its effectiveness. Oil refinery construction projects are risky because of technical complexity, resource unavailability, involvement of many stakeholders and strict environmental requirements. Although project risk management has been researched extensively, practical and easily adoptable framework is missing. In the proposed framework, risks are identified using cause and effect diagram, analysed using the analytic hierarchy process and responses are developed using the risk map. Additionally, decision tree analysis allows modelling various options for risk response development and optimises selection of risk mitigating strategy. The proposed risk management framework could be easily adopted and applied in any project and integrated with other project management knowledge areas.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

The main purpose of the study is to develop an integrated framework for managing project risks by analyzing risk across project, work package and activity levels, and developing responses. Design/methodology/approach: The study first reviews the literature of various contemporary risk management frameworks in order to identify gaps in project risk management knowledge. Then it develops a conceptual risk management framework using combined analytic hierarchy process (AHP) and risk map for managing project risks. The proposed framework has then been applied to a 1500 km oil pipeline construction project in India in order to demonstrate its effectiveness. The concerned project stakeholders were involved through focus group discussions for applying the proposed risk management framework in the project under study. Findings: The combined AHP and risk map approach is very effective to manage project risks across project, work package and activity levels. The risk factors in project level are caused because of external forces such as business environment (e.g. customers, competitors, technological development, politics, socioeconomic environment). The risk factors in work package and activity levels are operational in nature and created due to internal causes such as lack of material and labor productivity, implementation issues, team ineffectiveness, etc. Practical implications: The suggested model can be applied to any complex project and helps manage risk throughout the project life cycle. Originality/value: Both business and operational risks constitute project risks. In one hand, the conventional project risk management frameworks emphasize on managing business risks and often ignore operational risks. On the other hand, the studies that deal with operational risk often do not link them with business risks. However, they need to be addressed in an integrated way as there are a few risks that affect only the specific level. Hence, this study bridges the gaps. © 2010 Elsevier B.V. All rights reserved.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

A cross-country pipeline construction project is exposed to an uncertain environment due to its enormous size (physical, manpower requirement and financial value), complexity in design technology and involvement of external factors. These uncertainties can lead to several changes in project scope during the process of project execution. Unless the changes are properly controlled, the time, cost and quality goals of the project may never be achieved. A methodology is proposed for project control through risk analysis, contingency allocation and hierarchical planning models. Risk analysis is carried out through the analytic hierarchy process (AHP) due to the subjective nature of risks in construction projects. The results of risk analysis are used to determine the logical contingency for project control with the application of probability theory. Ultimate project control is carried out by hierarchical planning model which enables decision makers to take vital decisions during the changing environment of the construction period. Goal programming (GP), a multiple criteria decision-making technique, is proposed for model formulation because of its flexibility and priority-base structure. The project is planned hierarchically in three levels—project, work package and activity. GP is applied separately at each level. Decision variables of each model are different planning parameters of the project. In this study, models are formulated from the owner's perspective and its effectiveness in project control is demonstrated.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

Construction projects are complex endeavors that require the involvement of different professional disciplines in order to meet various project objectives that are often conflicting. The level of complexity and the multi-objective nature of construction projects lend themselves to collaborative design and construction such as integrated project delivery (IPD), in which relevant disciplines work together during project conception, design and construction. Traditionally, the main objectives of construction projects have been to build in the least amount of time with the lowest cost possible, thus the inherent and well-established relationship between cost and time has been the focus of many studies. The importance of being able to effectively model relationships among multiple objectives in building construction has been emphasized in a wide range of research. In general, the trade-off relationship between time and cost is well understood and there is ample research on the subject. However, despite sustainable building designs, relationships between time and environmental impact, as well as cost and environmental impact, have not been fully investigated. The objectives of this research were mainly to analyze and identify relationships of time, cost, and environmental impact, in terms of CO2 emissions, at different levels of a building: material level, component level, and building level, at the pre-use phase, including manufacturing and construction, and the relationships of life cycle cost and life cycle CO2 emissions at the usage phase. Additionally, this research aimed to develop a robust simulation-based multi-objective decision-support tool, called SimulEICon, which took construction data uncertainty into account, and was capable of incorporating life cycle assessment information to the decision-making process. The findings of this research supported the trade-off relationship between time and cost at different building levels. Moreover, the time and CO2 emissions relationship presented trade-off behavior at the pre-use phase. The results of the relationship between cost and CO2 emissions were interestingly proportional at the pre-use phase. The same pattern continually presented after the construction to the usage phase. Understanding the relationships between those objectives is a key in successfully planning and designing environmentally sustainable construction projects.

Relevância:

90.00% 90.00%

Publicador:

Resumo:

Privity of contract has lately been criticized in several European jurisdictions, particu-larly due to the onerous consequences it gives rise to in arrangements typical for the modern exchange such as chains of contracts. Privity of contract is a classical premise of contract law, which prohibits a third party to acquire or enforce rights under a contract to which he is not a party. Such a premise is usually seen to be manifested in the doctrine of privity of contract developed under common law, however, the jurisdictions of continental Europe do recognize a corresponding starting point in contract law. One of the traditional industry sectors affected by this premise is the construction industry. A typical large construction project includes a contractual chain comprised of an employer, a main contractor and a subcontractor. The employer is usually dependent on the subcontractor's performance, however, no contractual nexus exists between the two. Accordingly, the employer might want to circumvent the privity of contract in order to reach the subcontractor and to mitigate any risks imposed by such a chain of contracts. From this starting point, the study endeavors to examine the concept of privity of con-tract in European jurisdictions and particularly the methods used to circumvent the rule in the construction industry practice. For this purpose, the study employs both a com-parative and a legal dogmatic method. The principal aim is to discover general principles not just from a theoretical perspective, but from a practical angle as well. Consequently, a considerable amount of legal praxis as well as international industry forms have been used as references. The most important include inter alia the model forms produced by FIDIC as well as Olli Norros' doctoral thesis "Vastuu sopimusketjussa". According to the conclusions of this study, the four principal ways to circumvent privity of contract in European construction projects include liability in a chain of contracts, collateral contracts, assignment of rights as well as security instruments. The contempo-rary European jurisdictions recognize these concepts and the references suggest that they are an integral part of the current market practice. Despite the fact that such means of circumventing privity of contract raise a number of legal questions and affect the risk position of particularly a subcontractor considerably, it seems that the impairment of the premise of privity of contract is an increasing trend in the construction industry.

Relevância:

80.00% 80.00%

Publicador:

Resumo:

This document outlines a framework that could be used by government agencies in assessing policy interventions aimed at achieving social outcomes from government construction contracts. The framework represents a rational interpretation of the information gathered during the multi-outcomes construction policies project. The multi-outcomes project focused on the costs and benefits of using public construction contracts to promote the achievement of training and employment and public art objectives. The origin of the policy framework in a cost-benefit appraisal of current policy interventions is evidenced by its emphasis on sensitivity to policy commitment and project circumstances (especially project size and scope).The quantitative and qualitative analysis conducted in the multi-outcomes project highlighted, first, that in the absence of strong industry commitment to policy objectives, policy interventions typically result in high levels of avoidance activity, substantial administrative costs and very few benefits. Thus, for policy action on, for example, training or local employment to be successful compliance issues must be adequately addressed. Currently it appears that pre-qualification schemes (similar to the Priority Access Scheme) and schemes that rely on measuring, for example, the training investments of contractors within particular projects do not achieve high levels of compliance and involve significant administrative costs. Thus, an alternative is suggested in the policy framework developed here: a levy on each public construction project – set as a proportion of the total project costs. Although a full evaluation of this policy alternative was beyond the scope of the multi-outcomes construction policies project, it appears to offer the potential to minimize the transaction costs on contractors whilst enabling the creation of a training agency dedicated to improving the supply of skilled construction labour. A recommendation is thus made that this policy alternative be fully researched and evaluated. As noted above, the outcomes of the multi-outcomes research project also highlighted the need for sensitivity to project circumstances in the development and implementation of polices for public construction projects. Ideally a policy framework would have the flexibility to respond to circumstances where contractors share a commitment to the policy objectives and are able to identify measurable social outcomes from the particular government projects they are involved in. This would involve a project-by-project negotiation of goals and performance measures. It is likely to only be practical for large, longer term projects.

Relevância:

80.00% 80.00%

Publicador:

Resumo:

Recent developments in networked three dimensional (3D) virtual worlds, and the proliferation of high bandwidth communications technology, have the potential to dramatically improve collaboration in the construction industry. This research project focuses on the early stages of a construction project in which the models for the project are developed and revised. The project investigates three aspects of collaboration in virtual environments: 1. The processes that enable effective collaboration using high bandwidth information communication technology (ICT); 2. The models that allow for multiple disciplines to share their views in a synchronous virtual environment; 3. The generic skills used by individuals and teams when engaging with high bandwidth information communication technology. The third aspect of the project, listed above, led by the University of Newcastle, explores the domain of People and the extent to which they contribute to the effectiveness of virtual teams. This report relates, primarily, to this aspect.

Relevância:

80.00% 80.00%

Publicador:

Resumo:

Recent developments in networked three dimensional (3D) virtual worlds and the proliferation of high bandwidth communications technology have the potential to dramatically improve collaboration in the construction industry. This research project focuses on the early stages of a design/construction project in which models for a project are developed and revised. We have investigated three aspects of collaboration in virtual environments: 1. The processes that enable effective collaboration using high bandwidth information communication technology (ICT); 2. The models that allow for multiple disciplines to share their views in a synchronous virtual environment; 3. The generic skills used by individuals and teams when engaging with high bandwidth information communication technology.

Relevância:

80.00% 80.00%

Publicador:

Resumo:

Building Information Model (BIM) software, collaboration platforms and 5D Construction Management software is now commercially available and presents the opportunity for construction project teams to design more cost effectively, plan construction earlier, manage costs throughout the life cycle of a building project and provide a central asset management register for facilities managers. This paper outlines the merits of taking a holistic view of ICT in curriculum design. The educational barriers to implementation of these models and planning tools are highlighted. Careful choice of computer software can make a significant difference to how quickly students can master skills; how easy it is to study and how much they enjoy learning and be prepared for employment. An argument for BIM and 5D planning tools to be introduced into the curriculum to assist industry increase productivity and efficiencies are outlined by the authors.

Relevância:

80.00% 80.00%

Publicador:

Resumo:

Construction projects are faced with a challenge that must not be underestimated. These projects are increasingly becoming highly competitive, more complex, and difficult to manage. They become problems that are difficult to solve using traditional approaches. Soft Systems Methodology (SSM) is a systems approach that is used for analysis and problem solving in such complex and messy situations. SSM uses “systems thinking” in a cycle of action research, learning and reflection to help understand the various perceptions that exist in the minds of the different people involved in the situation. This paper examines the benefits of applying SSM to problems of knowledge management in construction project management, especially those situations that are challenging to understand and difficult to act upon. It includes five case studies of its use in dealing with the confusing situations that incorporate human, organizational and technical aspects.