21 resultados para planning project

em Aston University Research Archive


Relevância:

40.00% 40.00%

Publicador:

Resumo:

DUE TO COPYRIGHT RESTRICTIONS ONLY AVAILABLE FOR CONSULTATION AT ASTON UNIVERSITY LIBRARY AND INFORMATION SERVICES WITH PRIOR ARRANGEMENT

Relevância:

40.00% 40.00%

Publicador:

Resumo:

Projects exposed to an uncertain environment must be adapted to deal with the effective integration of various planning elements and the optimization of project parameters. Time, cost, and quality are the prime objectives of a project that need to be optimized to fulfill the owner's goal. In an uncertain environment, there exist many other conflicting objectives that may also need to be optimized. These objectives are characterized by varying degrees of conflict. Moreover, an uncertain environment also causes several changes in the project plan throughout its life, demanding that the project plan be totally flexible. Goal programming (GP), a multiple criteria decision making technique, offers a good solution for this project planning problem. There the planning problem is considered from the owner's perspective, which leads to classifying the project up to the activity level. GP is applied separately at each level, and the formulated models are integrated through information flow. The flexibility and adaptability of the models lies in the ease of updating the model parameters at the required level through changing priorities and/or constraints and transmitting the information to other levels. The hierarchical model automatically provides integration among various element of planning. The proposed methodology is applied in this paper to plan a petroleum pipeline construction project, and its effectiveness is demonstrated.

Relevância:

40.00% 40.00%

Publicador:

Resumo:

Projects that are exposed to uncertain environments can be effectively controlled with the application of risk analysis during the planning stage. The Analytic Hierarchy Process, a multiattribute decision-making technique, can be used to analyse and assess project risks which are objective or subjective in nature. Among other advantages, the process logically integrates the various elements in the planning process. The results from risk analysis and activity analysis are then used to develop a logical contingency allowance for the project through the application of probability theory. The contingency allowance is created in two parts: (a) a technical contingency, and (b) a management contingency. This provides a basis for decision making in a changing project environment. Effective control of the project is made possible by the limitation of the changes within the monetary contingency allowance for the work package concerned, and the utilization of the contingency through proper appropriation. The whole methodology is applied to a pipeline-laying project in India, and its effectiveness in project control is demonstrated.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

An inherent weakness in the management of large scale projects is the failure to achieve the scheduled completion date. When projects are planned with the objective of time achievement, the initial planning plays a vital role in the successful achievement of project deadlines. Cost and quality are additional priorities when such projects are being executed. This article proposes a methodology for achieving time duration of a project through risk analysis with the application of a Monte Carlo simulation technique. The methodology is demonstrated using a case application of a cross-country petroleum pipeline construction project.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

The development of an information system in Caribbean public sector organisations is usually seen as a matter of installing hardware and software according to a directive from senior management, without much planning. This causes huge investment in procuring hardware and software without improving overall system performance. Increasingly, Caribbean organisations are looking for assurances on information system performance before making investment decisions not only to satisfy the funding agencies, but also to be competitive in this dynamic and global business world. This study demonstrates an information system planning approach using a process-reengineering framework. Firstly, the stakeholders for the business functions are identified along with their relationships and requirements. Secondly, process reengineering is carried out to develop the system requirements. Accordingly, information technology is selected through detailed system requirement analysis. Thirdly, cost-benefit analysis, identification of critical success factors and risk analysis are carried out to strengthen the selection. The entire methodology has been demonstrated through an information system project in the Barbados drug service, a public sector organisation in the Caribbean.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

Purpose – The purpose of this paper is to help managers to successfully plan, implement, and operate enterprise resource planning (ERP) projects using a risk management framework. Design/methodology/approach – This paper adopted a combined literature review and case study method. Using literature review, the paper first identified major issues of managing ERP projects and develops a risk management framework for managing those issues. The proposed risk management framework was then applied to a ERP implementation project of a UK-based energy services group and its effectiveness for managing ERP projects implementation had been demonstrated. Additionally, the risk factors as identified from the case application are compared with the risk factors from the previous researches so as to suggest mitigating measures. Findings – All the risk factors are categorized into planning, implementation and operations phases along with project processes, organizational transformation and information technology (IT) perspectives. Project implementation phase is the most vulnerable to failure. The case study results reveal that the effect of other projects on on-going ERP project, management of overall IT architecture and non-availability of resources for organizational transformation are most critical from likelihood and impact perspectives. Managing risk across various phases of project and equal emphasize to effective project management, organizational transformation and IT adoption are the key to success in ERP implementation. Practical implications – The risk factors, which were identified using literature review and the case study, have great significance as mitigating measures of those risks may result successful implementation of ERP projects in the industry. Additionally, proposed risk management framework could be customized to implement ERP projects elsewhere. Originality/value – ERP projects are risky as they are capital intensive, technically complex, and call for organizational transformation. There are both success and failure stories. However, both researchers and practitioners agree, that if it can be implemented and operated successfully and benefits should be achievable. Although there are many studies on ERP implementation, little has been discussed on managing risks of ERP projects. Therefore, this paper bridges the gap.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

For many decades, the Kingdom of Saudi Arabia has been widely known for being a reliable oil exporter. This fact, however, has not exempted it from facing significant domestic energy challenges. One of the most pressing of these challenges involves bridging the widening electricity supply-demand gap where, currently, the demand is growing at a very fast rate. One crucial means to address this challenge is through delivering power supply projects with maximum efficiency. Project delivery delay, however, is not uncommon in this highly capital-intensive industry, indicating electricity supplies are not coping with the demand increases. To provide a deeper insight into the challenges of project implementation and efficient practice, this research adopts a pragmatic approach by triangulating literature, questionnaires and semi-structured interviews. The research was conducted in the Saudi Arabian power supply industry – Western Operating Area. A total of 105 usable questionnaires were collected, and 28 recorded, semi-structured interviews were conducted, analysed and synthesised to produce a conceptual model of what constitutes the project implementation challenges in the investigated industry. This was achieved by conducting a comprehensive ranking analysis applied to all 58 identified and surveyed factors which, according to project practitioners in the investigated industry, contribute to project delay. 28 of these project delay factors were selected as the "most important" ones. Factor Analysis was employed to structure these 28 most important project delay factors into the following meaningful set of 7 project implementation challenges: Saudi Electricity Company's contractual commitments, Saudi Electricity Company's communication and coordination effectiveness, contractors' project planning and project control effectiveness, consultant-related aspects, manpower challenges and material uncertainties, Saudi Electricity Company's tendering system, and lack of project requirements clarity. The study has implications for industry policy in that it provides a coherent assessment of the key project stakeholders' central problems. From this analysis, pragmatic recommendations are proposed that, if enacted, will minimise the significance of the identified problems on future project outcomes, thus helping to ensure the electricity supply-demand gap is diminished.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

This study highlights the variables associated with the implementation of renewable energy (RE) projects for sustainable development in India, by using an interpretive structural modeling (ISM) - based approach to model variables' interactions, which impact RE adoption. These variables have been categorized under enablers that help to enhance implementation of RE projects for sustainable development. A major finding is that public awareness regarding RE for sustainable development is a very significant enabler. For successful implementation of RE projects, it has been observed that top management should focus on improving highdriving power enablers (leadership, strategic planning, public awareness, management commitment, availability of finance, government support, and support from interest groups).

Relevância:

30.00% 30.00%

Publicador:

Resumo:

The aim of this research was to improve the quantitative support to project planning and control principally through the use of more accurate forecasting for which new techniques were developed. This study arose from the observation that in most cases construction project forecasts were based on a methodology (c.1980) which relied on the DHSS cumulative cubic cost model and network based risk analysis (PERT). The former of these, in particular, imposes severe limitations which this study overcomes. Three areas of study were identified, namely growth curve forecasting, risk analysis and the interface of these quantitative techniques with project management. These fields have been used as a basis for the research programme. In order to give a sound basis for the research, industrial support was sought. This resulted in both the acquisition of cost profiles for a large number of projects and the opportunity to validate practical implementation. The outcome of this research project was deemed successful both in theory and practice. The new forecasting theory was shown to give major reductions in projection errors. The integration of the new predictive and risk analysis technologies with management principles, allowed the development of a viable software management aid which fills an acknowledged gap in current technology.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

The work described in the following pages was carried out at various sites in the Rod Division of the Delta Metal Company. Extensive variation in the level of activity in the industry during the years 1974 to I975 had led to certain inadequacies being observed 1n the traditional cost control procedure. In an attempt to remedy this situation it was suggested that a method be found of constructing a system to improve the flexibility of cost control procedures. The work involved an assimilation of the industrial and financial environment via pilot studies which would later prove invaluable to home in on the really interesting and important areas. Weaknesses in the current systems which came to light made the methodology of data collection and the improvement of cost control and profit planning procedures easier to adopt. Because of the requirements of the project to investigate the implications of Cost behaviour for profit planning and control, the next stage of the research work was to utilise the on-site experience to examine at a detailed level the nature of cost behaviour. The analysis of factory costs then showed that certain costs, which were the most significant exhibited a stable relationship with respect to some known variable, usually a specific measure of Output. These costs were then formulated in a cost model, to establish accurate standards in a complex industrial setting in order to provide a meaningful comparison against which to judge actual performance. The necessity of a cost model was •reinforced by the fact that the cost behaviour found to exist was, in the main, a step function, and this complex cost behaviour, the traditional cost and profit planning procedures could not possibly incorporate. Already implemented from this work is the establishment of the post of information officer to co-ordinate data collection and information provision.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

This thesis deals with the integration of the manpower criterion with the strategic decision making processes of technological projects in developing countries. This integration is to be achieved by ensuring the involvement of the actors, who have relevant roles and responsibilities along the whole life cycle of the project, in the strategic decision making phases of the project. The relevance of the actors is ascertained by the use of a responsibility index which relates their responsibility to the project's constituent stages. In the context of a technological project in a typical centrally-planned developing environment, the actors are identified as Arbiters, Planners, Implementors and Operators and their roles, concerns and objectives are derived. In this context, the actors are usually government and non-government organisations. Hence, decision making will involve multiple agencies as well as multiple criteria. A methodology covering the whole decision-making process, from options generation to options selection, and adopting Saaty's Analytical Hierarchy Process as an operational tool is proposed to deal with such multiple-criteria, multipleagency decision situations. The methodology is intended to integrate the consideration of the relevant criteria, the prevailing environmental and policy factors, and the concerns and objectives of the relevant actors into a unifying decision-making process which strives to facilitate enlightened decision making and to enhance learning and interaction. An extensive assessment of the methodology's feasibility, based on a specific technological project within the Iraqi oil industry is included, and indicates that the methodology should be both useful and implementable.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

Modern injection-moulding machinery which produces several, pairs of plastic footwear at a time brought increased production planning problems to a factory. The demand for its footwear is seasonal but the company's manning policy keeps a fairly constant production level thus determining the aggregate stock. Production planning must therefore be done within the limitations of a specified total stock. The thesis proposes a new production planning system with four subsystems. These are sales forecasting, resource planning, and two levels of production scheduling: (a) aggregate decisions concerning the 'manufacturing group' (group of products) to be produced in each machine each week, and (b) detailed decisions concerning the products within a manufacturing group to be scheduled into each mould-place. The detailed scheduling is least dependent on improvements elsewhere so the sub-systems were tackled in reverse order. The thesis concentrates on the production scheduling sub-systems which will provide most. of the benefits. The aggregate scheduling solution depends principally on the aggregate stocks of each manufacturing group and their division into 'safety stocks' (to prevent shortages) and 'freestocks' (to permit batch production). The problem is too complex for exact solution but a good heuristic solution, which has yet to be implemented, is provided by minimising graphically immediate plus expected future costs. The detailed problem splits into determining the optimal safety stocks and batch quantities given the appropriate aggregate stocks. It.is found that the optimal safety stocks are proportional to the demand. The ideal batch quantities are based on a modified, formula for the Economic Batch Quantity and the product schedule is created week by week using a priority system which schedules to minimise expected future costs. This algorithm performs almost optimally. The detailed scheduling solution was implemented and achieved the target savings for the whole project in favourable circumstances. Future plans include full implementation.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

This research project has developed a novel decision support system using Geographical Information Systems and Multi Criteria Decision Analysis and used it to develop and evaluate energy-from-waste policy options. The system was validated by applying it to the UK administrative areas of Cornwall and Warwickshire. Different strategies have been defined by the size and number of the facilities, as well as the technology chosen. Using sensitivity on the results from the decision support system, it was found that key decision criteria included those affected by cost, energy efficiency, transport impacts and air/dioxin emissions. The conclusions of this work are that distributed small-scale energy-from-waste facilities score most highly overall and that scale is more important than technology design in determining overall policy impact. This project makes its primary contribution to energy-from-waste planning by its development of a Decision Support System that can be used to assist waste disposal authorities to identify preferred energy-from-waste options that have been tailored specifically to the socio-geographic characteristics of their jurisdictional areas. The project also highlights the potential of energy-from-waste policies that are seldom given enough attention to in the UK, namely those of a smaller-scale and distributed nature that often have technology designed specifically to cater for this market.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

Formulating manufacturing business strategy is often fragmented in as much as current tools address upstream and downstream vertical integration with product integration, or more recently, product and infrastructure integration. Rarely do tools address all of these dimensions in an holistic manner. The research described in this paper is that undertaken in the MAPSTRAT project: a scoping study with industrial partners, aiming to satisfy this business need. A comprehensive literature study is described which is contextualized using six case studies. The paper stresses the importance of ‘joined-up thinking’ and outlines plans for an appropriate tool that is under development.

Relevância:

30.00% 30.00%

Publicador:

Resumo:

This study proposes an integrated analytical framework for effective management of project risks using combined multiple criteria decision-making technique and decision tree analysis. First, a conceptual risk management model was developed through thorough literature review. The model was then applied through action research on a petroleum oil refinery construction project in the Central part of India in order to demonstrate its effectiveness. Oil refinery construction projects are risky because of technical complexity, resource unavailability, involvement of many stakeholders and strict environmental requirements. Although project risk management has been researched extensively, practical and easily adoptable framework is missing. In the proposed framework, risks are identified using cause and effect diagram, analysed using the analytic hierarchy process and responses are developed using the risk map. Additionally, decision tree analysis allows modelling various options for risk response development and optimises selection of risk mitigating strategy. The proposed risk management framework could be easily adopted and applied in any project and integrated with other project management knowledge areas.