26 resultados para Construction projects
em Aston University Research Archive
Resumo:
Purpose - The purpose of the paper is to the identify risk factors, which affect oil and gas construction projects in Vietnam and derive risk responses. Design/methodology/approach - Questionnaire survey was conducted with the involvement of project executives of PetroVietnam and statistical analysis was carried out in order to identify the major project risks. Subsequently, mitigating measures were derived using informal interviews with the various levels of management of PetroVietnam. Findings - Bureaucratic government system and long project approval procedures, poor design, incompetence of project team, inadequate tendering practices, and late internal approval processes from the owner were identified as major risks. The executives suggested various strategies to mitigate the identified risks. Reforming the government system, effective partnership with foreign collaborators, training project executives, implementing contractor evaluation using multiple criteria decision-making technique, and enhancing authorities of project people were suggested as viable approaches. Practical implications - The improvement measures as derived in this study would improve chances of project success in the oil and gas industry in Vietnam. Originality/value - There are several risk management studies on managing projects in developing countries. However, as risk factors vary considerably across industry and countries, the study of risk management for successful projects in the oil and gas industry in Vietnam is unique and has tremendous importance for effective project management.
Resumo:
Many planning and control tools, especially network analysis, have been developed in the last four decades. The majority of them were created in military organization to solve the problem of planning and controlling research and development projects. The original version of the network model (i.e. C.P.M/PERT) was transplanted to the construction industry without the consideration of the special nature and environment of construction projects. It suited the purpose of setting up targets and defining objectives, but it failed in satisfying the requirement of detailed planning and control at the site level. Several analytical and heuristic rules based methods were designed and combined with the structure of C.P.M. to eliminate its deficiencies. None of them provides a complete solution to the problem of resource, time and cost control. VERT was designed to deal with new ventures. It is suitable for project evaluation at the development stage. CYCLONE, on the other hand, is concerned with the design and micro-analysis of the production process. This work introduces an extensive critical review of the available planning techniques and addresses the problem of planning for site operation and control. Based on the outline of the nature of site control, this research developed a simulation based network model which combines part of the logics of both VERT and CYCLONE. Several new nodes were designed to model the availability and flow of resources, the overhead and operating cost and special nodes for evaluating time and cost. A large software package is written to handle the input, the simulation process and the output of the model. This package is designed to be used on any microcomputer using MS-DOS operating system. Data from real life projects were used to demonstrate the capability of the technique. Finally, a set of conclusions are drawn regarding the features and limitations of the proposed model, and recommendations for future work are outlined at the end of this thesis.
Resumo:
Numerous techniques have been developed to control cost and time of construction projects. However, there is limited research on issues surrounding the practical usage of these techniques. To address this, a survey was conducted on the top 150 construction companies and 100 construction consultancies in the UK aimed at identifying common project control practices and factors inhibiting effective project control in practice. It found that despite the vast application of control techniques a high proportion of respondents still experienced cost and time overruns on a significant proportion of their projects. Analysis of the survey results concluded that more effort should be geared at the management of the identified top project control inhibiting factors. This paper has outlined some measures for mitigating these inhibiting factors so that the outcome of project time and cost control can be improved in practice.
Resumo:
Construction projects are risky. However, the characteristics of the risk highly depend on the type of procurement being adopted for managing the project. A build-operate-transfer (BOT) project is recognized as one of the most risky project schemes. There are instances of project failure where a BOT scheme was employed. Ineffective rts are increasingly being managed using various risk management tools and techniques. However, application of those tools depends on the nature of the project, organization's policy, project management strategy, risk attitude of the project team members, and availability of the resources. Understanding of the contents and contexts of BOT projects, together with a thorough understanding of risk management tools and techniques, helps select processes of risk management for effective project implementation in a BOT scheme. This paper studies application of risk management tools and techniques in BOT projects through reviews of relevant literatures and develops a model for selecting risk management process for BOT projects. The application to BOT projects is considered from the viewpoints of the major project participants. Discussion is also made with regard to political risks. This study would contribute to the establishment of a framework for systematic risk management in BOT projects.
Resumo:
Construction projects are risky. A build-operate-transfer (BOT) project is recognised as one of the most risky project schemes. This scheme has been employed rather frequently in the past few decades, in both developed and developing countries. However, because of its risky nature, there have been failures as well as successes. Risk analysis in an appropriate way is desirable in implementing BOT projects. There are various tools and techniques applicable to risk analysis. The application of these risk analysis tools and techniques (RATTs) to BOT projects depends on an understanding of the contents and contexts of BOT projects, together with a thorough understanding of RATTs. This paper studies key points in their applications through reviews of relevant literatures and discusses the application of RATTs to BOT projects. The application to BOT projects is considered from the viewpoints of the major project participants, i.e. government, lenders and project companies. Discussion is also made with regard to political risks, which are very important in BOT projects. A flow chart has been introduced to select an appropriate tool for risk management in BOT projects. This study contributes to the establishment of a framework for systematic risk management in BOT projects.
Resumo:
Conventional project management techniques are not always sufficient for ensuring time, cost and quality achievement of large-scale construction projects due to complexity in planning and implementation processes. The main reasons for project non-achievement are changes in scope and design, changes in Government policies and regulations, unforeseen inflation) under-estimation and improper estimation. Projects that are exposed to such an uncertain environment can be effectively managed with the application of risk numagement throughout project life cycle. However, the effectiveness of risk management depends on the technique in which the effects of risk factors are analysed and! or quantified. This study proposes Analytic Hierarchy Process (AHP), a multiple attribute decision-making technique as a tool for risk analysis because it can handle subjective as well as objective factors in decision model that are conflicting in nature. This provides a decision support system (DSS) to project managenumt for making the right decision at the right time for ensuring project success in line with organisation policy, project objectives and competitive business environment. The whole methodology is explained through a case study of a cross-country petroleum pipeline project in India and its effectiveness in project1nana.gement is demonstrated.
Resumo:
Conventional project management techniques are not always sufficient to ensure time, cost and quality achievement of large-scale construction projects due to complexity in planning, design and implementation processes. The main reasons for project non-achievement are changes in scope and design, changes in government policies and regulations, unforeseen inflation, underestimation and improper estimation. Projects that are exposed to such an uncertain environment can be effectively managed with the application of risk management throughout the project's life cycle. However, the effectiveness of risk management depends on the technique through which the effects of risk factors are analysed/quantified. This study proposes the Analytic Hierarchy Process (AHP), a multiple attribute decision making technique, as a tool for risk analysis because it can handle subjective as well as objective factors in a decision model that are conflicting in nature. This provides a decision support system (DSS) to project management for making the right decision at the right time for ensuring project success in line with organisation policy, project objectives and a competitive business environment. The whole methodology is explained through a case application of a cross-country petroleum pipeline project in India and its effectiveness in project management is demonstrated.
Resumo:
The thesis addresses the economic impacts of construction safety in Greece. The research involved the development of a methodology for determining the overall costs of safety, namely the sum of the costs of accidents and the costs of safety management failures (with or without accident) including image cost. Hitherto, very little work has been published on the cost of accidents in practical case studies. Moreover, to the author’s belief, no research has been published that seeks to determine in real cases the costs of prevention. The methodology developed is new, transparent, and capable of being replicated and adapted to other employment sectors and to other countries. The methodology was applied to three construction projects in Greece to test the safety costing methodology and to offer some preliminary evidence on the business case for safety. The survey work took place between 1999 and 2001 and involved 27 months of costing work on site. The study focuses on the overall costs of safety that apply to the main (principal) contractor. The methodology is supported by 120 discrete cost categories, and systematic criteria for determining which costs are included (counted) in the overall cost of safety. A quality system (in compliance with ISO9000 series) was developed to support the work and ensure accuracy of data gathering. The results of the study offer some support for the business case for safety. Though they offer good support for the economics of safety as they demonstrate need for cost effectiveness. Subject to important caveats, those projects that appeared to manage safety more cost-effectively achieved the lowest overall safety cost. Nevertheless, results are significantly lower than of other published works for two main reasons; first costs due to damages with no potential to injury were not included and second only costs to main constructor were considered. Study’s results are discussed and compared with other publish works.
Resumo:
Despite the availability of various control techniques and project control software many construction projects still do not achieve their cost and time objectives. Research in this area so far has mainly been devoted to identifying causes of cost and time overruns. There is limited research geared towards studying factors inhibiting the ability of practitioners to effectively control their projects. To fill this gap, a survey was conducted on 250 construction project organizations in the UK, which was followed by face-to-face interviews with experienced practitioners from 15 of these organizations. The common factors that inhibit both time and cost control during construction projects were first identified. Subsequently 90 mitigating measures have been developed for the top five leading inhibiting factors—design changes, risks/uncertainties, inaccurate evaluation of project time/duration, complexities and non-performance of subcontractors were recommended. These mitigating measures were classified as: preventive, predictive, corrective and organizational measures. They can be used as a checklist of good practice and help project managers to improve the effectiveness of control of their projects.
Resumo:
Conventional project management techniques are not always sufficient to ensure that schedule, cost and quality goals are met on large-scale construction projects. These jobs require complex planning, designing and implementation processes. The main reasons for a project's nonachievement in India's hydrocarbon processing industry are changes in scope and design, altered government policies and regulations, unforeseen inflation, under and/or improper estimation. Projects that are exposed to such an uncertain environment can be effectively managed by applying risk management throughout the project life cycle.
Resumo:
A cross-country pipeline construction project is exposed to an uncertain environment due to its enormous size (physical, manpower requirement and financial value), complexity in design technology and involvement of external factors. These uncertainties can lead to several changes in project scope during the process of project execution. Unless the changes are properly controlled, the time, cost and quality goals of the project may never be achieved. A methodology is proposed for project control through risk analysis, contingency allocation and hierarchical planning models. Risk analysis is carried out through the analytic hierarchy process (AHP) due to the subjective nature of risks in construction projects. The results of risk analysis are used to determine the logical contingency for project control with the application of probability theory. Ultimate project control is carried out by hierarchical planning model which enables decision makers to take vital decisions during the changing environment of the construction period. Goal programming (GP), a multiple criteria decision-making technique, is proposed for model formulation because of its flexibility and priority-base structure. The project is planned hierarchically in three levels—project, work package and activity. GP is applied separately at each level. Decision variables of each model are different planning parameters of the project. In this study, models are formulated from the owner's perspective and its effectiveness in project control is demonstrated.
Resumo:
The construction industry is susceptible to extreme weather events (EWEs) due to most of its activities being conducted by manual workers outdoors. Although research has been conducted on the effects of EWEs, such as flooding and snowfall, limited research has been conducted on the effects of heatwaves and hot weather conditions. Heatwaves present a somewhat different risk profile to construction, unlike EWEs such as flooding and heavy snowfall that present physical obstacles to work onsite. However, heatwaves have affected the construction industry in the UK, and construction claims have been made due to adverse weather conditions. With heatwaves being expected to occur more frequently in the coming years, the construction industry may suffer unlike any other industry during the summer months. This creates the need to investigate methods that would allow construction activities to progress during hot summer months with minimal effect on construction projects. Hence, the purpose of this paper. Regions such as the Middle East and the UAE in particular flourish with mega projects, although temperatures soar to above 40̊C in the summer months. Lessons could be learnt from such countries and adapted in the UK. Interviews have been conducted with a lead representative of a client, a consultant and a contractor, all of which currently operate on UAE projects. The key findings include one of the preliminary steps taken by international construction companies operating in the UAE. This involves restructuring their entire regional team by employing management staff from countries such as Lebanon, Palestine, Iraq, and their labour force from the sub-continent such as India and Pakistan. This is not only due to the cheap wage rate but also to the ability to cope and work in such extreme hot weather conditions. The experience of individuals working in the region allows for future planning, where the difference in labour productivity during the extreme hot weather conditions is known, allowing precautionary measures to be put in place.
Resumo:
The aim of this study is to address the main deficiencies with the prevailing project cost and time control practices for construction projects in the UK. A questionnaire survey was carried out with 250 top companies followed by in-depth interviews with 15 experienced practitioners from these companies in order to gain further insights of the identified problems, and their experience of good practice on how these problems can be tackled. On the basis of these interviews and syntheses with literature, a list of 65 good practice recommendations have been developed for the key project control tasks: planning, monitoring, reporting and analysing. The Delphi method was then used, with the participation of a panel of 8 practitioner experts, to evaluate these improvement recommendations and to establish their degree of relevance. After two rounds of Delphi, these recommendations are put forward as "critical", "important", or "helpful" measures for improving project control practice.
Resumo:
Risks and uncertainties are part and parcel of any project as projects are planned with many assumptions. Therefore, managing those risks is the key to project success. Although risk is present in all most all projects, large-scale construction projects are most vulnerable. Risk is by nature subjective. However, managing risk subjectively posses the danger of non-achievement of project goals. This study introduces an analytical framework for managing risk in projects. All the risk factors are identified, their effects are analyzed, and alternative responses are derived with cost implication for mitigating the identified risks. A decision-making framework is then formulated using decision tree. The expected monetary values are derived for each alternative. The responses, which require least cost is selected. The entire methodology has been explained through a case study of an oil pipeline project in India and its effectiveness in managing projects has been demonstrated. © INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING.
Resumo:
Time, cost and quality achievements on large-scale construction projects are uncertain because of technological constraints, involvement of many stakeholders, long durations, large capital requirements and improper scope definitions. Projects that are exposed to such an uncertain environment can effectively be managed with the application of risk management throughout the project life cycle. Risk is by nature subjective. However, managing risk subjectively poses the danger of non-achievement of project goals. Moreover, risk analysis of the overall project also poses the danger of developing inappropriate responses. This article demonstrates a quantitative approach to construction risk management through an analytic hierarchy process (AHP) and decision tree analysis. The entire project is classified to form a few work packages. With the involvement of project stakeholders, risky work packages are identified. As all the risk factors are identified, their effects are quantified by determining probability (using AHP) and severity (guess estimate). Various alternative responses are generated, listing the cost implications of mitigating the quantified risks. The expected monetary values are derived for each alternative in a decision tree framework and subsequent probability analysis helps to make the right decision in managing risks. In this article, the entire methodology is explained by using a case application of a cross-country petroleum pipeline project in India. The case study demonstrates the project management effectiveness of using AHP and DTA.