Microsoft Project is one of the most-widely used software packages for project management. For the scheduling of resource-constrained projects, the package applies a priority-based procedure using a specific schedule-generation scheme. This procedure performs relatively poorly when compared against other software packages or state-of-the-art methods for resource-constrained project scheduling. In Microsoft Project 2010, it is possible to work with schedules that are infeasible with respect to the precedence or the resource constraints. We propose a novel schedule-generation scheme that makes use of this possibility. Under this scheme, the project tasks are scheduled sequentially while taking into account all temporal and resource constraints that a user can define within Microsoft Project. The scheme can be implemented as a priority-rule based heuristic procedure. Our computational results for two real-world construction projects indicate that this procedure outperforms the built-in procedure of Microsoft Project