151 resultados para Port Quequén


Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on the Port Dalhousie and Thorold Railway by Messrs. Brown and McDonell, contractors, on sections 1, 2, and 3 ending at St. Catharines for the month of Nov., 1855. This document is water damaged and full of holes. The list of prices is almost completely illegible. The document is signed by S.D. Woodruff, Dec. 1855.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate for work done on the Port Dalhousie and Thorold Railway by John Brown, contractor regarding the section between Geneva Street and the Thorold Station for the month of Dec. 1855. This document is burned on the right hand side. This affects the text slightly. It is signed by S.D. Woodruff, Jan. 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart and a memo (4 pages, handwritten) regarding the Port Dalhousie and Thorold Railway from Port Dalhousie to St. Catharines. This is an explanation reflecting the differences between the approximate and final estimate. The memo is slightly stained and the chart is slightly torn. This does not affect the text, Jan. 2, 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Mr. Woodward’s timetable regarding the suspension bridge to Toronto via the Great Western Railway and Port Dalhousie Railway (1 page, handwritten), Jan. 22, 1856

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and Thorold Station of the Grantham Railway by John Brown for February, 1856. This is signed by S.D. Woodruff, engineer, March 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and Thorold Station of the Grantham Railway by John Brown for March, April and May 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and Thorold Station of the Grantham Railway by John Brown for May, 1856. This is signed by S.D. Woodruff, engineer, June 3, 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate for work done on the Port Dalhousie and Thorold Railway by John Brown, contractor regarding the section between Geneva Street and the Thorold Station up to the 30th of June 1856. This document is burned on the edges. This does not affect the text, 1856

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Port Dalhousie and Thorold Railway wages paid to John Brown (2 pages, handwritten) from Aug. 1855 – May 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and Thorold Station of the Great Western Railway by John Brown for July, 1856. This is accompanied by a chart of an itemized list and a sheet of calculations, Aug. 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate of work done on Port Dalhousie and Thorold Railway in the section between Geneva Street and the Thorold Station of the Great Western Railway by John Brown for August, 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Chart of estimate for work done on the Port Dalhousie and Thorold Railway by Alex Morrison regarding construction of the coal wharf for the month of Jul. 1856. The document is signed by S.D. Woodruff, Aug. 24, 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Letter to the Port Dalhousie and Thorold Railway for work the sluice at the aqueduct, on the hillside. This is signed by R. Collier, Aug. 28, 1856.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Memorandum of material furnished for superstructure on the line of the Port Dalhousie Thorold Railway by contract. This document includes: Bills of timber, memorandums of planking, fencing, ties, track laying, masonry and bolts and spikes. There are also diagrams of culverts. One of the pages is loose and the outer pages are somewhat discoloured (32 pages, handwritten and bound with ribbon, n.d.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Schedule of prices for Brown and McDonell, contractors, for sections 1, 2 and 3 of the Port Dalhousie Thorold Railway (1 page, handwritten), Sept. 24, 1856.