178 resultados para Mortar and concrete
Resumo:
Portland cement concrete (PCC) pavements have given excellent service history for Iowa. The first concrete pavement was placed in Le Mars in 1904 and was in service until 1968. The Eddyville Cemetery Road placed in 1909 is still in service today. Many other pavements placed during the 1920s and 1930s are still in service today. The objective of this report is to document various changes in specifications, pavement design and equipment for PCC paving from the early 1900s to present. This includes changes that were made to the specification book and supplemental specifications. Where possible, information is given as a basis for the change in specifications.
Resumo:
This report presents the results of the largest and most comprehensive study to date on portland cement pervious concrete (PCPC). It is designed to be widely accessible and easily applied by designers, producers, contractors, and owners. The project was designed to begin with pervious concrete best practices and then to address the unanswered questions in a systematic fashion to allow a successful overlay project. Consequently, the first portion of the integrated project involved a combination of fundamental material property investigations, test method development, and addressing constructability issues before actual construction could take place. The second portion of the project involved actual construction and long-term testing before reporting successes, failures, and lessons learned. The results of the studies conducted show that a pervious concrete overlay can be designed, constructed, operated, and maintained. A pervious concrete overlay has several inherent advantages, including reduced splash and spray and reduced hydroplaning potential, as well as being a very quiet pavement. The good performance of this overlay in a particularly harsh freeze-thaw climate, Minnesota, shows pervious concrete is durable and can be successfully used in freeze-thaw climates with truck traffic and heavy snow plowing.
Resumo:
Data collection to determine the rate of bond strength development between concrete overlays and existing pavements and the evaluation of nondestructive testing methods for determining concrete strength were the objectives of this study. Maturity meters and pulse velocity meters were employed to determine the rate of flexural strength gain and determine the time for opening of newly constructed pavements to traffic. Maturity measurements appear to provide a less destructive method of testing. Pulse velocity measurements do require care in the preparation of the test wells and operator care in testing. Both devices functioned well under adverse weather and construction conditions and can reduce construction traffic delay decisions. Deflection testing and strain gaging indicate differences in the reaction of the overlay and existing pavement under grouting versus nongrouted sections. Grouting did enhance the rate of bond development with Type I11 cement out performing the Type I1 grout section. Type I11 and Type I1 cement grouts enhanced resistance to cracking in uniformly supported pavements where joints are prepared prior to overlays achieving target flexural strengths. Torsional and direct shear testing provide additional ways of measuring bond development at different cure times. Detailed data analysis will be utilized by TRANSTEC, Inc. to develop a bonded overlay construction guidelines report.
Resumo:
The purpose of this guide is to help practitioners understand how to optimize concrete pavement joint performance through the identification, mitigation, and prevention of joint deterioration. It summarizes current knowledge from research and practice to help practitioners access the latest knowledge and implement proven techniques. Emphasizing that water is the common factor in most premature joint deterioration, this guide describes various types of joint deterioration that can occur. Some distresses are caused by improper joint detailing or construction, and others can be attributed to inadequate materials or proportioning. D cracking is a form of joint distress that results from the use of poor-quality aggregates. A particular focus in this guide is joint distress due to freeze-thaw action. Numerous factors are at play in the occurrence of this distress, including the increased use of a variety of deicing chemicals and application strategies. Finally, this guide provides recommendations for minimizing the potential for joint deterioration, along with recommendations for mitigation practices to slow or stop the progress of joint deterioration.
Resumo:
This guide provides a summary of the factors and design theories that should be considered when designing dowel load transfer systems for concrete pavement systems (including dowel basket design and fabrication) and presents recommendations for widespread adoption (i.e., standardization). Development of the guide was sponsored by the National Concrete Consortium with the goal of helping practitioners develop and implement dowel load transfer designs based on knowledge about current research and best practices.
Resumo:
Developed as a more detailed follow up at a 2009 briefing document,Building Sustainable Pavement with Concrete, this guide provides a clear, concise and cohesive discussion of pavement sustainability concepts and of recommended practices for maximizing the sustainability of concrete pavements. The intended audience includes decisions makers and practitioners in both owner-agencies and supply, manufacturing consulting and contractor businesses. Readers will find individual chapters with the most recent technical information and best practices related to concrete pavement deign, materials, construction, use/operations, renewal and recycling. In addition, they will find chapters addressing issues specific to pavement sustainability in the urban environment and to the evaluation of pavement sustainability.
Resumo:
General principles • Everyone at the construction site, particularly foremen and supervisors, is responsible for recognizing and troubleshooting potential problems as they arise. • Batches of concrete should be consistent and uniformly mixed. • A major cause of pavement failure is unstable subgrade. The subgrade should consist of uniform material, and the subgrade system must drain well. • Dowel bars are important for load transfer at transverse joints on pavements with high truck volumes. Dowels must be carefully aligned, horizontally and vertically, to prevent pavement damage at the joints. • Stringlines control the slipform paver’s horizontal and vertical movement and ensure a smooth pavement profile. Once stringlines are set, they should be checked often and not disturbed. • Overfinishing the new pavement and/or adding water to the surface can lead to pavement surface problems. If the concrete isn’t sufficiently workable, crews should contact the project manager. Changes to the mixture or to paver equipment may reduce the problem. • Proper curing is critical to preventing pavement damage from rapid moisture loss at the pavement surface. • A well spaced and constructed system of joints is critical to prevent random cracking. • Joints are simply controlled cracks. They must be sawed during the brief time after the pavement has gained enough strength to prevent raveling but before it begins to crack randomly (the “sawing window”). • Seasonal and daily weather variations affect setting time and other variables in new concrete. Construction operations should be adjusted appropriately.
Resumo:
This document provides language that can be used by an Owner-Agency to develop materials and construction specifications with the objective of reducing tire/pavement noise. While the practices described herein are largely prescriptive, they have been demonstrated to increase the likelihood of constructing a durable, quieter concrete surface.
Resumo:
This practice provides guidance and example specification language intended for use by Owner-Agencies in development of specific contract language when requiring the evaluation of tire/pavement noise for new concrete pavement surfaces. The overall sound intensity level is designated as the quality characteristic used for pay adjustment.
Resumo:
The Greene County, Iowa overlay project, completed in October 1973, was inspected on October 16 & 17, 1978 After five years of service The 33 fibrous concrete sections, four CRCP sections, two mesh reinforced and two plain concrete sections with doweled reinforcement were rated relative to each other on a scale of 0 t o 100. The rating was conducted by the original members of the Project Planning Committee, Iowa DOT, Iowa Counties, Federal Highway Administration, University of Illinois and industry representatives . In all , there were 23 representatives who rated this project . The 23 values were then averaged to provide a final rating number for each section. The highest panel rating (90) was assigned to the 5-inch thick , deformed barre in forced PCC sections ; an 86t o a 3-inch thick , 160 lbs. of fiber and 600 lbs . of cement on a partial bonded surface ; an 84 to the 4-inch CRC with elastic joints (bonded) and an 84 to a 4-inch mesh reinforce section. One of the major factors influencing performance appears t o be the thickness. In the fibrous concrete overlay, The greatest influences appears t o be the fiber content. Overlay Sections containing 160 1b/yd3 of Fiber are, in almost all cases , outperforming those c o n t a i n i n g 60 or 100. It is obvious at This time meth at the 3-inch thick fibrous concrete overlays are, in general, out performing the 2-inch thick sections. The performance of the fibrous concrete the overlay appears to be favorably influenced by: (1) The use of higher a spectra fiber (0.025 x 2.5 i n c h e s ) v e r s u s (0.010 x 0.022 x 1.0 inches) (2) The use of a lower cement c o n t e n t ( 600 versus 750 1b/yd3) However, The set less well defined and the improvements in overlay performance attributed to high aspect ratio fibers and low cement contents.
Resumo:
The objectives of this research project are: (1) To determine the feasibility of proportioning, mixing, placing and finishing a dense portland cement concrete in a bridge floor using conventional mixing, placing and finishing equipment. (2) To determine the economics, longevity, maintenance performance and protective qualities of a dense portland cement concrete bridge floor when using a high rangewater reducing admixture. The purpose of a high range water reducing admixture is to produce a dense, high quality concrete at a low water-cement ratio witj adequate workability. A low water-cement ratio contributes greatly to increased strength. The normal 7 day strength of untreated concrete would be expected i n 3 days using a superplasticizer. A dense concrete also has the desirable properties of excellent durability and reduced permeability. It is felt that a higher quality, denser, higher strength portland cement concrete can be produced and placed, using conventional equipment, by the addition of a high range water reducing admixture. Such a dense concrete, w i t h a water/cement ratio of approximately 0.30 to 0.35, would be expected to be much less permeable and thus retard the intrusion of chloride. With care and attention given to obtaining the design cover over steel (2% inches clear), it i s hoped that protection for the design life of the structure will be obtained. Evaluation of this experimental concrete bridge floor included chloride content and delamination testing of the concrete floor five years after construction. A comparitive evaluation o f a control section o f concrete without the water reducing admixture was conducted. Other items o f comparison include workability during construction, strength, density, water-cement ratio and chloride penetration.
Resumo:
Iowa has the same problem that confronts most states in the United States: many bridges constructed more than 20 years ago either have deteriorated to the point that they are inadequate for original design loads or have been rendered inadequate by changes in design/maintenance standards or design loads. Inadequate bridges require either strengthening or posting for reduced loads. A sizeable number of single span, composite concrete deck - steel I beam bridges in Iowa currently cannot be rated to carry today's design loads. Various methods for strengthening the unsafe bridges have been proposed and some methods have been tried. No method appears to be as economical and promising as strengthening by post-tensioning of the steel beams. At the time this research study was begun, the feasibility of posttensioning existing composite bridges was unknown. As one would expect, the design of a bridge-strengthening scheme utilizing post-tensioning is quite complex. The design involves composite construction stressed in an abnormal manner (possible tension in the deck slab), consideration of different sizes of exterior and interior beams, cover-plated beams already designed for maximum moment at midspan and at plate cut-off points, complex live load distribution, and distribution of post-tensioningforces and moments among the bridge beams. Although information is available on many of these topics, there is miminal information on several of them and no information available on the total design problem. This study, therefore, is an effort to gather some of the missing information, primarily through testing a half-size bridge model and thus determining the feasibility of strengthening composite bridges by post-tensioning. Based on the results of this study, the authors anticipate that a second phase of the study will be undertaken and directed toward strengthening of one or more prototype bridges in Iowa.
Resumo:
Research project HR-219 was sponsored by the Iowa Highway Research Board and the Iowa Department of Transportation. The funding authorized from the Primary Road Research Fund was $11,200. The author wishes to express his appreciation to Iowa DOT personnel for their participation in the research. The special features were incorporated into the plans by Road Design personnel. Office of Materials personnel developed the proportions for the flowable mortar. Project inspection was provided by the Creston Resident Engineer and his staff. The excellent cooperation of the contractors contributed to the success of the research. The prime contractor was Irving F. Jensen Company, Inc. of Sioux City, Iowa who retained Reilly Construction Company of Ossian, Iowa and GNA Concrete, Inc. of Grimes, Iowa as subcontractors for the special culvert backfilling.
Resumo:
In the past, many pier columns were deteriorating due to attack by chlorides. The chloride (from deicers) has attacked the substructures by drainage from the superstructure. Piers supporting grade separation bridges are also subject to chlorides contained in the direct splash from lower level traffic. Repairs of these piers are both difficult and costly. In this project, four different sealants were applied to piers to evaluate their use in the protection of the concrete against chloride-ions. One pier was left untreated to use as a control pier with which to compare the protected piers. This project began in 1980 and was to be completed in 1985, but at that time it was determined further testing was needed to make a more conclusive evaluation.
Resumo:
Safety i s a very important aspect o f the highway program. The Iowa DOT initiated an inventory o f the friction values of all paved primary roadways i n 1969. This inventory, with an ASTM E-274 test unit, has continued to the present time. The t e s t i n g frequency varies based upon traffic volume and the previous friction value. Historically , the state o f Iowa constructed a substantial amount o f pcc pavement during the 1928-30 period t o "get Iowa out o f the mud". Some of that pavement has never been resurfaced and has been subjected to more than 50 years o f wear. The textured surface has been worn away and has subsequently polished. Even though some pavements from 15 t o 50 years old continue t o function structurally , because of the loss of friction , they do not provide the desired level o f safety to the driver. As a temporary measure, "Sl ippery -When -Wet " signs have been posted on many older pcc roads due to friction numbers below t h e desirable level. These signs warn the motorist of the current conditions. An economical method of restoring the high quality frictional properties i s needed.