82 resultados para Sergel, Johan Tobias, 1740-1814.

em Harvard University


Relevância:

20.00% 20.00%

Publicador:

Resumo:

Contains one sewn volume of work orders for the construction of University Hall in the hand of Loammi Baldwin between May 1813 and May 1814. The volume contains 46 completed work orders for supplies and services for "building the new Dining Halls and Chapel in Cambridge" payable to Hon. John Davis, Harvard treasurer. Completed work orders are noted with the name of the payee, amount paid, and the supplies or services fulfilled. Work orders 47 through 60 in the volume are unused.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Lee, a Boston merchant who often represented the city as deputy in the Massachusetts General Court, asks Baldwin if the laborers laying the bricks and stone for University Hall could be loaned for a few days to work on the construction of the South meeting house [New South Church].

Relevância:

20.00% 20.00%

Publicador:

Resumo:

This is a contract signed between Loammi Baldwin, acting on behalf of the President and Fellows of Harvard College, and Josiah Moore, John Walton, Thomas Mason, Samuel Mason, and Joseph Holmes for completing the dining rooms and chapel of University Hall. The agreement was witnessed by Abraham Edwards and Thomas Edwards.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Draft of the official signed copy of the contract in Box 1, Folder 42. This copy is written in a different hand and contains several struck through phrases.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Lowell discusses the selection of a painter for the interior of University Hall with Baldwin.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Cary writes Baldwin with questions about the size of marble window stools to be installed in University Hall.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Signed by President John Kirkland, this Corporation vote acknowledges that Loammi Baldwin has given his notice that he can no longer oversee the construction of University Hall. The Corporation votes to pay him seven hundred dollars for his services.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

This contract includes stipulations for finishing the two kitchens, windows, and floors in University Hall by the first of August 1815.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Estimate for $10,189.62 to complete stone work in University Hall. This includes the front basement, end basement, window stools, door ports, and stairs.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Estimate for $5942.68 for the completion of the interior fixtures of University Hall including folding doors, pew arrangement in the chapel, and architraves to doors, windows, and fireplaces.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Detailed list of twelve interior projects that need to be completed in University Hall. The list includes hinging doors, completing architraves, and installing windows. Appears to be simplified version of Memoranda of contract with carpenters, Moore, and others, in Box 1, Folder 42.

Relevância:

20.00% 20.00%

Publicador:

Resumo:

Known as the Bulfinch view, this proposed site plan of the College grounds by Charles Bulfinch depicts University Hall at the center of the drawing surrounded by Massachusetts, Harvard, Hollis, Stoughton, and Holworthy Halls. Several unlabeled buildings are displayed in the plan.