An open pit multistage mine production scheduling model for drilling, blasting and excavating operations


Autoria(s): Kozan, Erhan; Liu, Shi Qiang
Data(s)

2014

Resumo

This paper proposes a new multi-resource multi-stage scheduling problem for optimising the open-pit drilling, blasting and excavating operations under equipment capacity constraints. The flow process is analysed based on the real-life data from an Australian iron ore mine site. The objective of the model is to maximise the throughput and minimise the total idle times of equipment at each stage. The following comprehensive mining attributes and constraints have been considered: types of equipment; operating capacities of equipment; ready times of equipment; speeds of equipment; block-sequence-dependent movement times of equipment; equipment-assignment-dependent operation times of blocks; distances between each pair of blocks; due windows of blocks; material properties of blocks; swell factors of blocks; and slope requirements of blocks. It is formulated by mixed integer programming and solved by ILOG-CPLEX optimiser. The proposed model is validated with extensive computational experiments to improve mine production efficiency at the operational level. The model also provides an intelligent decision support tool to account for the availability and usage of equipment units for drilling, blasting and excavating stages.

Formato

application/pdf

Identificador

http://eprints.qut.edu.au/79573/

Publicador

AusIMM Press

Relação

http://eprints.qut.edu.au/79573/1/Kozan_and_Liu_AusIMM_SMP_2014.pdf

https://www.ausimm.com.au/publications/content/orebody_2014.pdf

Kozan, Erhan & Liu, Shi Qiang (2014) An open pit multistage mine production scheduling model for drilling, blasting and excavating operations. In Orebody Modelling and Strategic Mine Planning 2014, AusIMM Press, Perth, Western Australia, pp. 329-334.

Direitos

Copyright 2014 please consult author(s).

Fonte

School of Mathematical Sciences; Science & Engineering Faculty

Palavras-Chave #010206 Operations Research #091405 Mining Engineering #Open-Pit #Multi-Stage #Mine Production Scheduling #Drilling, Blasting and Excavating
Tipo

Conference Paper